Our New School: Phase 2

June 16, 2017
As you can see when you come to school, progress with Phase 2 of the new build - the demolition of the old building, levelling of the site, installation of the Junior playground, the new field, main entrance footpath from Chepstow Avenue and landscaping - is all going very well.

The new Junior playground was completed during the half term break; pupils have been excited to use it over the last two weeks. Demolition of the old school was completed at the beginning of this week and construction works are levelling the site prior to commencing landscaping, installation of footpaths, the school field etc. It is anticipated that all works will be completed around October 2017.

We hope, therefore, that by very early in the 2017/18 academic year our brand new £10.5 million school will be complete.